Cary, NC
Pedestrian Tunnel
under CSXT Railroad
The White Oak Creek Greenway project for the Town of Cary consisted of the construction of approximately 0.5 miles of pedestrian improvements consisting of approximately 1,191 lf of concrete greenway. 102 lf of 14-ft diameter pedestrian tunnel under CSXT railroad, 916 lf of concrete boardwalk, and 355 lf of concrete sidewalk, 916 lf of concrete boardwalk.
Turn-Key Tunneling was subcontracted to construct 102 lf of 14-ft diameter pedestrian tunnel under CSXT railroad.